Timeline

Tuesday March 26, 2013
  • Hole Dug
Wednesday March 27, 2013
  • Footers In
Thursday March 28, 2013
  • Foundation Walls
April 1-5 2013
  • French Drain
  • Molds off
  • Plumbing Rough ins
  • Basement and Garage Floor Poured
April 8-10
  • Lumber Delivery
  • Stood up by Framers :(
April 11-14
  • Framers show up :)
  • First floor done and a few exterior walls 
April 15-17
  • First and Second floor Exterior walls windows
  • Most interior walls in
  • Roof structure complete
April 18-26
  • Exterior Insulation completed
  • Framing completed
  • HVAC started
  • Plumbing
  • Guardian (walk through April 24) 
  • Garage door installed
April 29-30
  • Electric completed
  • HVAC completed
  • Plumbing completed
  • Guardian Installation
  • Door Handles
  • Prep for front porch floor
Wednesday May 1, 2013
  •  Pre-drywall walk through